The El Dorado City Commission approved the Ballpark Improvement Plan in December 2022, which includes upgrades at Central Fields, East Park Fields and McDonald Stadium.
Start Date: December 2022
Completion Date: 2024
Total Estimated Cost: $2.062 Million
-
Snell Field in East Park
-
Concession stands at Central Park Ballfield
-
McDonald Stadium Fence
-
McDonald Stadium Turf Replacement
-
East Park Concession Demolition
-
McDonald Stadium Turf Replacement
-
McDonald Stadium Turf Replacement
December 2022 - City Commission approves use of Excess Sales Tax Dollars to fund a four-year ballpark improvement project
Spring 2023 - Request for bids for McDonald Stadium fence project
April 2023 - Request for proposal for Central and East Park Concession and restroom facilities
May 2023 - Concession and restroom project awarded to Conco Construction
June 2023 - Request for proposal for McDonald Stadium turf project
- McDonald Stadium outfield fence project awarded to Champion Wall Systems and Kansas Fencing
July 2023 - McDonald Stadium turf project awarded to Hellas Construction to replace infield turf
- Central and East park concession/restroom facilities in design process
August 2023 - Work begins at McDonald Stadium to replace turf
- McDonald Stadium fence in design process
- Construction begins on Central and East concession/restroom facilities
September 2023 - McDonald Stadium turf completed
- Start of fence construction at McDonald Stadium
- Start of site preparation for concession stands at Central and East ballfields
October 2023 - Construction underway on McDonald Stadium fence
- Construction continues on concession stands
November 2023 - Scoreboards installed at six of seven facilities at East Park and Central ballfields; the remaining one will be installed in August
- Outfield fence at McDonald Stadium completed
December 2023 - Delivery of McDonald Stadium scoreboard
- Concession/restroom construction underway - completion expected in early February
January 2024 - Construction begins on Hamblin Field fence and bullpen
February 2024 - Installation underway for McDonald Stadium scoreboard
- Construction continues on East Park concession/restroom facilities
- Installation of new netting and repair of the backstop frame at McDonald Stadium
- Removal of wood outfield fence at Hamblin Field (this will be replaced with a chain link fence with wind slats)
March 2024 - Final walk-through of East Park concession stand completed
- Final walk-through at Central Park concession stand
- Installation continues on McDonald Stadium scoreboard
- Work underway on backstops at Mitchell and Red Day Fields
April 2024 - Work continues on backstops at Central Park; Hamblin field will be next
May 2024 - Work is being finished on the concession stands at East Park and Central Ball Fields. Work is completed on all backstops
August 2024 - Planning and price quotes for seating at McDonald Stadium
- Drainage work, installation of irrigation and common area maintenance at East Park
September 2024 - Irrigation repair and common area maintenance at Central Park
2025-2026 - Anticipated projects through 2026 include:
- Common area irrigation at East park
- Restroom refresh at McDonald Stadium
- Seating replacement and other repairs at McDonald Stadium
- Backstop repairs at Mitchell Field, Snell Field and North Field at East Park and the Walnut River Complex
- Bullpen construction at Hamblin Field
- Several fence replacements
McDonald Stadium Project Expenses
Estimated Total $906,000
Estimated Actual
- Turf and Mound Replacement - $315,000 $335,500
- Outfield Fence - $200,000 $179,054
- Facade Updating - $150,000
- Bleacher Benches - $100,000
- Other Building Improvements - $96,000
- Scoreboard and Backstop - $45,000
Central Park Ballfield Project Expenses
Estimated Total $610,000
Estimated Actual
- Concession/Restroom Facility - $300,000 $299,974
- Field Fences - $225,000
- Scoreboards and Lighting - $36,000
- Backstops and Bullpens - $24,000
- Irrigation and Shade Structures - $25,000
East Park Ballfield Project Expenses
Estimated Total $546,000
Estimated Actual
- Concession/Restroom Facility - $300,000 $299,974
- Fences - $100,000
- Orndorff Bleacher Pad - $100,000
- Scoreboards (Orndorff & Snell) - $14,000
- Backstops and Bullpens - $12,000
- Shade Structures - $20,000
-
Community Impact
The fields at McDonald Stadium and Central and East Park ballfields are used by our recreational leagues, El Dorado High School, Butler Community College and the El Dorado Walnuts, as well as for other special events throughout the year.